Physical Progress

Physical Progress

Section-01:

Component %Weightage as per Schedule-G Progress achieved (during current month) Physical Progress achieved (Cumulative, up to current month)
Road works including culverts, minor bridges, underpasses, overpasses, approaches to ROB/RUB/ Major Bridges/ Structures (but excluding service roads) 34.70%    
Major Bridge Works & ROB/ RUB 33.97%    
Structures (elevated sections, reinforced earth) 12.08%    
Electrical and Public Health Utilities 1.58%    
Other Works 17.67%    
Total 100.00%    

Section-02:

Component %Weightage as per Schedule-G Progress achieved (during current month) Physical Progress achieved (Cumulative, up to current month)
Road works including culverts, minor bridges, underpasses, overpasses, approaches to ROB/RUB/ Major Bridges/ Structures (but excluding service roads) 55.89%    
Major Bridge Works & ROB/ RUB      
Structures (elevated sections, reinforced earth) 8.14%    
Electrical and Public Health Utilities      
Other Works 35.97%    
Total 100.00%